Question: a . Choose the correct network diagram below. b . Calculate the critical path for this project. The critical path is and the project duration

a. Choose the correct network diagram below.
b. Calculate the critical path for this project.
The critical path is
and the project duration is 25 days. (Enter your response as a whole number.)
c. How much slack is in each of the activities G,H, and I?
The first two have been answered, how much slack for G,H, and I?