Question: A class team project is assigned that requires building a spreadsheet model. Figuring out the details of what the instructor is asking in the project

A class team project is assigned that requires building a spreadsheet model.
Figuring out the details of what the instructor is asking in the project fall in the initiation phase.
Building a prototype spreadsheet model as a first pass to meet the project requirements is part of the planning phase.
Discussing the results of the modeling work so far is a part of the control phase.
Completing the project reflection assignment is part of project execution phase.
Exactly two answers are correct.
None of the answers are correct.