Question: A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10
A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month 10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million. Which statement most accurately portrays program status? A. Behind schedule, pay application accurately reflects percentage complete. B. On schedule, pay application exceeds percentage complete. C. Behind schedule, pay application exceeds percentage complete. D. On schedule, pay application accurately reflects percentage complete
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
