Question: A company has 3 machining centre (A, B and C) and 3 new jobs (1, 2 and 3) to complete. The cost of performing
A company has 3 machining centre (A, B and C) and 3 new jobs (1, 2 and 3) to complete. The cost of performing the individual job in each machine centre are mentioned in table. Do the job assignment for minimum cost [7] Job 1 Job 2 Job 3 Machining Centre A Machining Centre B Machining Centre C 15 10 12 10 10 12 15 10 8 025
Step by Step Solution
★★★★★
3.40 Rating (144 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
The solution to the problem in the image is to assign jobs 1 and 2 to machining ... View full answer