A Company has budgeted N20,000,000 to produce 100 units of Office tables in 100 days. After 50
Fantastic news! We've Found the answer you've been seeking!
Question:
A Company has budgeted N20,000,000 to produce 100 units of Office tables in 100 days. After 50 days, only 40 units have been produced and N4,500,000 has been expended. Using Earned Value analysis, determine if the project is:
1. Over budget or not
2. On or behind schedule