Question: A company has to make a choice between two projects namely A & B. The initial capital outlay of two projects are $365,000 and $568,000

A company has to make a choice between two projects namely A & B. The initial capital outlay of two projects are $365,000 and $568,000 respectively for A and B. There will be no scrap value at the end of the life of both the projects. The opportunity cost of capital of the company is 16%. The annual income are as under: Year Project A Project B 1 15000 8500

2 23000 11100

3 27500 15200

4 19600 14700

5 18400 22500

6 23400 28100

7 35200 39200

8 38100 50400

9 39000 82400

10 45150 79200

11 46800 98640

12 48630 110800

13 52180 61400

14 50280 70560

15 61890 52400

There will be additional cash outflow of $23,000 and $31,000 at the end of 8 year for project A and B respectively. Analyze which project is better for the company using following approaches: 1. Net present value 2. Payback period 3. Discounted payback period 4. Profitability index

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!