Question: A company has traditionally allocated its overhead based on machine hours but had collected this information to change to activity-based costing: Estimated ActivityActivity CenterProduct 1Product
A company has traditionally allocated its overhead based on machine hours but had collected this information to change to activity-based costing:
Estimated ActivityActivity CenterProduct 1Product 2Estimated CostMachine Setups1545$9,600Assembly Parts4,5004,500216,900Packaging Pieces50040055,350Machine Hours per Unit43Production Volume7501,500