Question: A company has traditionally allocated its overhead based on machine hours but had collected this information to change to activity-based costing: Estimated Activity Activity Center

A company has traditionally allocated its overhead based on machine hours but had collected this information to change to activity-based costing: Estimated Activity Activity Center Product 1 Product 2 Estimated Cost Machine Setups 15 45 $ 11,400 Assembly Parts 4,500 4,500 215,100 Packaging Pieces 500 400 54,900 Machine Hours per Unit 4 3 Production Volume 750 1,500 A. How much overhead would be allocated to each unit under the traditional allocation method? Round your answers to two decimal places. Product 1 Product 2 Allocation per unit $ B. How much overhead would be allocated to each unit under activity-based costing? Round your answers to two decimal places. Product 1 Product 2 Allocation per unit $ $