Question: A company identifies a potential security risk with the implementation of a new system. After assessing the risk, the company decides to halt the deployment
A company identifies a potential security risk with the implementation of a new system. After assessing the risk, the company decides to halt the deployment and not to proceed with the systems introduction to avoid the risks altogether. What risk management strategy is the company employing?
AExemption
BTransference
CMitigation
DAvoidance