Question: A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $871.71
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:
0 1 2 3 4 Project S -$1,000 $871.71 $260 $10 $15
Project L -$1,000 $0 $260 $380 $824.11
The company's WACC is 10.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.