Question: A company is considering two projects, A and B, with the following projected cash flows and IRRs: Year Project A Cash Flow ($) Project B
A company is considering two projects, A and B, with the following projected cash flows and IRRs:
Year | Project A Cash Flow ($) | Project B Cash Flow ($) |
0 | -50,000 | -70,000 |
1 | 20,000 | 25,000 |
2 | 30,000 | 35,000 |
3 | 40,000 | 50,000 |
IRR | 22% | 24% |
The company's cost of capital is 10%.
a) Calculate the NPV of each project. b) Which project should be chosen based on NPV? c) Explain why NPV is a better measure than IRR. d) If the cost of capital increases to 15%, how would the decision change?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
