Question: A company is interested in developing a quarterly aggregate production plan but they are not sure if a level strategy with backorders or a chase
A company is interested in developing a quarterly aggregate production plan but they are not sure if a level strategy with backorders or a chase strategy would be better. They have the following information available regarding their production operation:
| Hiring Cost (per unit increase) | $40 |
| Firing (per unit decrease) | $80 |
| Inventory Cost (per unit) | $40 |
| Stockout (per unit) | $150 |
| Production (Labor) cost (per unit) | $30 |
| Subcontracting cost (per unit) | $60 |
| Previous quarter's production | 1300 |
| Previous quarter's ending inventory | 0 |
Quarter forecasts are 4000, 2000, 4000 and 5000, respectively.
Suppose that you want to use a chase plan. What is the labor cost of quarter 1? (Do not round your intermediate calculations. Round your final answer to the nearest whole number.)
A. 90000
B. 120000
C. 60000
D. 150000
E. None of these