Question: A company is using a fixed order quantity inventory system. The lead time for replenishment deliveries is 6 weeks. The demand over a 2 week

A company is using a fixed order quantity inventory system. The lead time for
replenishment deliveries is 6 weeks. The demand over a 2 week period is estimated to be 100 units, with
a standard deviation of 20 units. Please assume that demand is normally distributed.
What is the reorder point that will provide a 95% service level?