Question: A company operating under a continuous review system has an average demand of 50 units per week for the item it produces. The standard deviation
A company operating under a continuous review system has an average demand of 50 units per week for the item it produces. The standard deviation in weekly demand is 20 units. The lead-time for the item is six weeks, and it costs the company $30 to process each order. The holding cost for each unit is $10 per year. The company operates 52 weeks per year. (for z values refer to normal distribution table in the textbook, pg 599 OR you can use excel functions)