Question: A company produces heating elements that go through two operations, casting and assembling, before they are complete. Expected costs and activities for the two departments

A company produces heating elements that go through two operations, casting and assembling, before they are complete. Expected costs and activities for the two departments are shown below. Given this information, calculate the departmental overhead rate for the assembling department based on direct labor hours. Casting Assembling Direct labor hours 1,875 DLH 7,500 DLH Machine hours 12,500 MH 3,750 MH Overhead costs $75,000 $37,500 ROUND YOUR ANSWER WITH ZERO DECIMAL PLACES IF THE ANSWER IS $10 PER DIRECT LABOR HOUR, JUST WRITE 10