Question: A company that assembles generators has the policy to maintain a WIP of 2 0 0 generators in their plant. Given that a generator is

A company that assembles generators has the policy to maintain a WIP of 200 generators in their plant. Given that a generator is produced every 3 minutes, what is the lead time to complete a generator build?
5 minutes
6 minutes
5 hours
10 minutes
10 hours
6 hours
minute
 A company that assembles generators has the policy to maintain a