Question: A companys planned activity level for next year is expected to be 100000 machine hours. At this level of activity, the company budgeted the following
A companys planned activity level for next year is expected to be 100000 machine hours. At this level of activity, the company budgeted the following manufacturing overhead costs:
| Variable | Fixed | |||
| Indirect materials | $130000 | Depreciation | $37500 | |
| Indirect labor | 150000 | Taxes | 7500 | |
| Factory supplies | 18000 | Supervision | 30000 | |
A flexible budget prepared at the 90000 machine hours level of activity would show total manufacturing overhead costs of
|
| $335700. |
|
| $298000. |
|
| $268200. |
|
| $343200. |