Question: A companys planned activity level for next year is expected to be 50,000 machine hours. At this level of activity, the company budgeted the following
-
A companys planned activity level for next year is expected to be 50,000 machine hours. At this level of activity, the company budgeted the following manufacturing overhead costs:
Variable Fixed
Indirect materials $90,000 Depreciation $37,500
Indirect labor 120,000 Taxes 7,500
Factory supplies 15,000 Supervision 30,000
A flexible budget prepared at the 90,000 machine hours level of activity would show total manufacturing overhead costs of
$405,000
$480,000
$477,500
$425,000