Question: A completes a work in 4 days whereas B completes the work in 6 days. C works 112 times as fast as A. How many
A completes a work in 4 days whereas B completes the work in 6 days. C works 112 times as fast as A. How many days it will take for the three together to complete the work ?
a. 712
b. 1512
c. 157
d. None of these
Step by Step Solution
There are 3 Steps involved in it
The detailed answer for the above question ... View full answer
Get step-by-step solutions from verified subject matter experts