Question: A complex project requires the delivery of 10 electronic boxes. The first box took 220 hours to assemble. The learning rate is 10% (90% learning

A complex project requires the delivery of 10 electronic boxes.

The first box took 220 hours to assemble.

The learning rate is 10% (90% learning curve).

What is the estimated cost to assemble all 10 units? The hourly labor rate is $194. Round your answer to the nearest dollar, if applicable.