Question: a. Consider a company that produces a given article, through a set of operations with the precedence indicated in the table (daily work of 8h).
a. Consider a company that produces a given article, through a set of operations with the precedence indicated in the table (daily work of 8h).
Construct the circulation graph of an in-line deployment (sequential posts) that shows the highest possible efficiency, without considering the single post hypothesis.
| Operation | Op. time | Precedences |
| A | 1 | - |
| B | 1,2 | A- |
| C | 0,6 | B |
| D | 1,2 | C |
| E | 0,8 | D |
| F | 1,4 | E |
| G | 1,6 | F |
| H | 0,2 | G |
| I | 0,6 | H |
| J | 1,2 | I |
| K | 1,2 | J |
| L | 1 | K |
b. Assume that a given improvement proposal involves an investment of $5,000, the hiring of an additional specialized operator paid at $5/hour and an increase in energy consumption by an additional $1/hour. Knowing that the gain per hour with this improvement is $10/hour, determine after what number of working hours the investment becomes viable.