Question: A) Construct the Activity on Node (AON) network diagram for the project data given below. B) Compute & show on the Expanded Node diagram
A) Construct the Activity on Node (AON) network diagram for the project data given below. B) Compute & show on the Expanded Node diagram the Early Start ES, Early Finish EF, Late Start LS, Late Finish LF and Total Float TF timing. (as per the standard legend) C) Determine the Critical Path and Total Project Duration. ACTIVITY PRECEDESSOR DURATION A B C D E F G H A A B C C D, E F, G 3 4 2 5 1 2 4 3
Step by Step Solution
3.33 Rating (147 Votes )
There are 3 Steps involved in it
A AON network diagram A B C B D C E C F D E G F G ... View full answer