Question: A . Construct the AON network for this problem. B . Determine the ES , EF , LS , LF times for each activity. Construct

A.Construct the AON network for this problem.
B. Determine the ES, EF, LS, LF times for each activity. Construct a box alongside each activity.
Activity Duration ES EF LS LF
A 90909
B 2911911
C 129211325
D 521262126
E 621272127
F 827352735
G 335383538
H 29113638
I 838463846
C. Construct a table which determines the slack for each activity.
Activity Slack
A 0
B 0
C 0
D 0
E 0
F 0
G 0
H 25
I 0
d. Which activities are on the critical path? Explain how you know this.
e. What is the time of the critical path?
f. What is the slack time for activity F? What is the importance of this value?
 A.Construct the AON network for this problem. B. Determine the ES,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!