Question: A . Construct the AON network for this problem. B . Determine the ES , EF , LS , LF times for each activity. Construct
AConstruct the AON network for this problem.
B Determine the ES EF LS LF times for each activity. Construct a box alongside each activity.
Activity Duration ES EF LS LF
A
B
C
D
E
F
G
H
I
C Construct a table which determines the slack for each activity.
Activity Slack
A
B
C
D
E
F
G
H
I
d Which activities are on the critical path? Explain how you know this.
e What is the time of the critical path?
f What is the slack time for activity F What is the importance of this value?