Question: A construction company is negotiating on a construction project with a six month duration. On the last day of each month the construction company may
A construction company is negotiating on a construction project with a six month duration. On the last day of each month the construction company may bill the Owner for the work completed during the month. The Owner pays the monthly bills one month after they are received. Final payment is expected one month after completion of the project. The construction company pays material suppliers in full when it receives payment from the owner. The company pays subcontractors when it receives payment. The construction company pays for labor weekly. The projected monthly material, labour and subs costs as well as the amount the company will bill the Owner each month arc shown in the following table. Determine the monthly cash flow. How much profit was earned