Question: A construction company is preparing a PERT network for laying the foundation of a new art museum. Given the following set of activities, their predecessor

A construction company is preparing a PERT network for laying the foundation of a new art museum. Given the following set of activities, their predecessor requirement and three estimates of completion time : [ 8 ] MBAMBFMBEC202 Activities Predecessors Time estimates (days) Optimistic Pessimistic Most Likely A B C D E F G H I J K NONE NONE A B C C C, D F, G E I H 2 8 7 6 9 10 11 6 4 3 1 4 8 11 6 11 18 11 14 6 5 1 3 8 9 6 10 14 11 10 5 4 1 (i) Draw PERT network. (ii) Compute the slack for each activity and determine the critical path