Question: A construction company is preparing for a nine-month project, and will need to develop a staffing plan. The company can assign up to 30 of

A construction company is preparing for a nine-month project, and will need to develop a staffing plan. The company can assign up to 30 of its own full-time employees to the project, and will hire short-term contract employees to make up any shortage in meeting the personnel requirements. Company employees earn $6,000 per month, while short-term contract employees make $8,600/month. Contract employees can be assigned to the project beginning in any month, and their contract period is two months. The number of workers required for the project by month is shown below:

Month of Project 49 Required 15 23 59 65 7177 64 43 21 6


Determine the optimal staffing plan for the project.

Month of Project 2 3 4 5 6. 7 8. 6. Required 15 23 59 65 71 77 64 43 21 1.

Step by Step Solution

3.45 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The optimal plan is as follows Month 1 2 4 6 7 9 Required Headcount FTES Required STCS Required 15 2... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!