Question: A construction company is tasked with building a bridge over a river. The project is scheduled to take 1 8 0 days. However, due to
A construction company is tasked with building a bridge over a river. The project is scheduled to take days. However, due to unexpected delays, the construction team completes only of the bridge in the first days. Assuming the remaining work progresses at a constant rate, what is the estimated total duration needed to finish the bridge?