Question: A construction manager is responsible for developing a new site for residential home construction. He has identified the following activities, their predecessor activities, and their
A construction manager is responsible for developing a new site for residential home construction. He has identified the following activities, their predecessor activities, and their expected duration:
| Task | Predecessors | Duration (Days) |
| A. Final Purchase | 2 | |
| B. Surveying | A | 4 |
| C. Permitting | A | 6 |
| D. Road Grading | B, C | 5 |
| E. Electrical Lines | C | 4 |
| F. Storm and Sewer | D | 7 |
| G. Paving | E, F | 6 |
| H. Tree Removal | E | 2 |
| I. Clearing Lots | G, H | 6 |
| J. City Inspection | I | 2 |
- Draw the network diagram representing this project.
- use the forward and backward pass method to label the network in full. give a full schedule table activity (es, ef, ls,lf, and slack)
- identify critical path and project completion time.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts