Question: A construction manager is responsible for developing a new site for residential home construction. He has identified the following activities, their predecessor activities, and their

A construction manager is responsible for developing a new site for residential home construction. He has identified the following activities, their predecessor activities, and their expected duration:

Task Predecessors Duration (Days)
A. Final Purchase 2
B. Surveying A 4
C. Permitting A 6
D. Road Grading B, C 5
E. Electrical Lines C 4
F. Storm and Sewer D 7
G. Paving E, F 6
H. Tree Removal E 2
I. Clearing Lots G, H 6
J. City Inspection I 2
  1. Draw the network diagram representing this project.
  2. use the forward and backward pass method to label the network in full. give a full schedule table activity (es, ef, ls,lf, and slack)
  3. identify critical path and project completion time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!