Question: A construction project is broken down into following activities as listed below: Activity Immediate predecessors Expected time (weeks) A ----- 7 B A 5 C

A construction project is broken down into following activities as listed below:

Activity

Immediate predecessors

Expected time (weeks)

A

-----

7

B

A

5

C

B,G

6

D

C,F

6

E

A

4

F

E

8

G

E

3

Question 28 (4 points)

What is the critical path?

Question 28 options:

A-E-F-D

A-E-C-G-D

A-E-G-C-D

A-B-C-D

Question 29 (4 points)

How many weeks will the project take to complete?

Question 29 options:

27

25

26

24

Question 30 (4 points)

Suppose F could be shortened by one week and B could be shortened by two weeks, then the critical path would be:

Question 30 options:

A-E-G-C-D

A-E-F-D

A-E-C-G-D

A-B-C-D

Question 31 (4 points)

Based on Q31, what the completion date of the project would be?

Question 31 options:

22

23

24

26

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!