Question: A construction project is broken down into following activities as listed below: Activity Immediate predecessors Expected time (weeks) A ----- 7 B A 5 C
A construction project is broken down into following activities as listed below:
| Activity | Immediate predecessors | Expected time (weeks) |
| A | ----- | 7 |
| B | A | 5 |
| C | B,G | 6 |
| D | C,F | 6 |
| E | A | 4 |
| F | E | 8 |
| G | E | 3 |
Question 28 (4 points)
What is the critical path?
Question 28 options:
| A-E-F-D | |
| A-E-C-G-D | |
| A-E-G-C-D | |
| A-B-C-D |
Question 29 (4 points)
How many weeks will the project take to complete?
Question 29 options:
| 27 | |
| 25 | |
| 26 | |
| 24 |
Question 30 (4 points)
Suppose F could be shortened by one week and B could be shortened by two weeks, then the critical path would be:
Question 30 options:
| A-E-G-C-D | |
| A-E-F-D | |
| A-E-C-G-D | |
| A-B-C-D |
Question 31 (4 points)
Based on Q31, what the completion date of the project would be?
Question 31 options:
| 22 | |
| 23 | |
| 24 | |
| 26 |