Question: A construction project is broken down into the following 1 0 activities: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) 1 4 2 1 2 3

A construction project is broken down into the following 10 activities:
ACTIVITY IMMEDIATE
PREDECESSOR TIME (WEEKS)
14
212
314
413
52,35
636
742
853
96,75
108,97
b-1. Find the critical path.
multiple choice
1-4-7-9-10
1-3-5-8-10
1-2-5-8-10
1-3-6-9-10
b-2. How many weeks will the project take to complete?