Question: A construction project is broken down into the following 10 activities: IMMEDIATE ACTIVITY PREDECESSOR TIME (WEEKS) 1 4 2 1 2 3 1 4 4


A construction project is broken down into the following 10 activities: IMMEDIATE ACTIVITY PREDECESSOR TIME (WEEKS) 1 4 2 1 2 3 1 4 4 1 3 5 2.3 5 6 3 6 7 4 2 8 5 3 9 6,7 5 10 8,9 7 b-1. Find the critical path. O 1-3-5-8-10 O 1-2-5-8-10 1-4-7-9-10 1-3-6-9-10 b-2. How many weeks will the project take to complete? Number of weeks c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which activities would you shorten to cut the project by four weeks? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) ? Cut activity 3 by 3 weeks, and then reduce activity 6 or 9 by one week. 2 Cut activity 5 by 4 weeks. 2 Reduce activities 6 and 9 by a total of 3 weeks, and then reduce activity 3 by one week. Cut activity 4 by 3 weeks, and then reduce activity 6 or 5 by one week. ? Cut activity 5 by 3 weeks, and then reduce activity 4 or 9 by one week
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
