Question: A construction project is carried out by a general contractor with the following descriptions: Project Duration: 3 months (Start: May 1st; End: July 31st) Contract

A construction project is carried out by a general contractor with the following descriptions:

  • Project Duration: 3 months (Start: May 1st; End: July 31st)
  • Contract Amount: 125,216+135,925+155,906+146,583+166,863+173,309+138,537+206,949+221,267
  • Budget Amount: 428,161+520,781+578,151
  • Contract Terms and Conditions
    • Materials: The construction company pays material suppliers in full when it receives payment from the owner. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received.
    • Labor: The construction company pays for labor on the 25th of each month.
    • Subcontractor: The construction company pays subcontractors when it receives payment from the owner but withholds 5% from the subcontractors payment. Final payment will include payment of the retention.
    • Between the contractor and the owner: On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received. The owner withholds 5% from the construction company's payment. Final payment will include payment of the retention.
  • Cost-loaded schedule and billing schedule to the owner
Month May June July
Cost-Loaded Schedule Materials 125,216 135,925 155,906
Labor 146,583 166,863 173,309
Subcontractor 138,537 206,949 221,267
Bill to Owner 428,161 520,781 578,151

What is the cash flow on June 30th?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!