Question: A construction project is waiting on material delivery that has been delayed. This is external to the project and could impact the project even though
A construction project is waiting on material delivery that has been delayed. This is external to the project and could impact the project even though this task is not part of the performance measurement baseline. This lag could be represented in the project plan as a task with a description. These tasks are called