A consultant engineer has undertaken a project for a client. The project aim is to establish a
No answer yet for this question.
Ask a Tutor
Question:
A consultant engineer has undertaken a project for a client. The project aim is to establish a maintenance helpdesk function in the clients organisation. The tasks involved are outlined in Table Q3c below. Using Table Q3c, draw the network diagram and determine the following, showing all calculations: i)Total project duration ii) Critical path. Explain why it is important for the Project Manager to identify the critical path.