Question: A consulting firm that is developing an information system for an insurance firm to make a transition to a paperless organization has identified the following
A consulting firm that is developing an information system for an insurance firm to make a transition to a "paperless" organization has identified the following activities:

Activity Duration (months) Immediate Activity Predecessor Optimistic Most Likely Pessimistic 16 DE.G a. Draw the project network showing the activities with their expected times. b. What is the critical path and the expected duration of the project? c. What is the probability of completing the project within 2 years? English (United States) Focus E EIP 238 9.56.14 57 29
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts