A contr act has 90 days remaining until completion.Each completion will be paidn$18,000 bonus per day that the duration is shortened.Activities on the critical path are targeted for crashing.Critical activiities can be accelerated by allocating additional crew as shown on the table below.If crews must be added as a complete unit, the net bonus is maximized by the addtion of how many crews?