Question: A contractor doesn't like your vertical curve and asks you to give him the elevation at STA 1 1 + 5 0 . Your design

A contractor doesn't like your vertical curve and asks you to give him the elevation at STA 11+50. Your design was a curve with length of 500Ft, Starting Elevation of 437.50, the PVI is at STA 10+00 with an Elevation of 450.00Ft, and G2=-1%.