Question: A contractor in Lisbon has six jobs awaiting processing. Processing time and due dates of each job are given in the table. Assume that jobs

 A contractor in Lisbon has six jobs awaiting processing. Processing time

A contractor in Lisbon has six jobs awaiting processing. Processing time and due dates of each job are given in the table. Assume that jobs arrive in the order shown. Set the processing sequence according to FCFS and SPT, and provide a recommendation base on the 1) average completion time, ii) average number of jobs in system, ili) average job lateness, and iv) utilization. Start date is day 1 Job A Due Data 22 14 30 B Processing Time 6 12 14 2 10 4 D E F 25 34