Question: A contractor is excavating a site for a basement construction. The total volume of excavation is 1 5 , 0 0 0 y d 3

A contractor is excavating a site for a basement construction. The total volume of
excavation is 15,000yd3 in dense sand. The void ratio of the soil at site is 0.5 and the
degree of saturation is 30%. When the material is excavated, the sand loosened and the
void ratio increased to 0.8.
a. To haul away the excavated soil, the contractor is using trucks which have a
maximum capacity of 10yd3. How many truck loads of soil will have to be hauled
away, if the full capacity of the truck is utilized? [Ans.1,800 loads]
b. According to city ordinance, the maximum legal weight that trucks can carry is 10
tons. Can the truck driver be cited if he is carrying soil to the maximum capacity (by
volume)? Assume specific gravity of soil solids to be 2.65.[Ans. Yes. Soil weight is
13.1 ton]
A contractor is excavating a site for a basement

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!