Question: A contractor must install 3 2 , 4 3 2 sf of carpet for a new office building that is being constructed. The contractor bid
A contractor must install sf of carpet for a new office building that is being constructed. The contractor bid the project at $sf If the contractor has working days to complete the project, and the contractor assumes the same amount of work will be performed each day to complete the work, but by the end of day the contractor has installed sf what will the SPI for the project be to that point?