Question: A contractor must install 5 1 , 7 5 5 If of silt fence for a new 3 0 0 acre industrial site being constructed.

A contractor must install 51,755 If of silt fence for a new 300 acre industrial site being constructed. The contractor bid the project at $7.28? If. If the contractor has 10 working days to complete the installation, and the contractor assumes the same amount of work will be performed each day to complete the work, but by the end of day 5, the contractor has spent $180,303, what will the CPI for the project be to that point?
 A contractor must install 51,755 If of silt fence for a