Question: A contractor placed a column footing in the wrong spot due to an error that the contractor's surveyor made when laying out the column locations.
A contractor placed a column footing in the wrong spot due to an error that the contractor's surveyor made when laying out the column locations. The contractor will have to tear out part of the incorrect footing, and put in a new footing in the correct location. Under a cost plus contract is the contractor entitled to payment for the costs of partially demolishing the existing footing and pouring the new footing? No Yes