Question: A contractor refuses to complete a house for $ 1 5 0 , 0 0 0 because he has already spent that amount in building

A contractor refuses to complete a house for $150,000 because he has already spent that
amount in building the house. He demands an additional $50,000 from the owner to complete
the house even though the contract calls for a completed house for $150,000. If the owner agrees
to his demand
a. This additional promise is unenforceable because of pre existing legal duty
b. This additional promise is unenforceable because of past consideration
c. This additional promise is enforceable