Question: A cost that should be ignored when evaluating a project because that cost has already been incurred and cannot be recouped is referred to as
A cost that should be ignored when evaluating a project because that cost has already been incurred and cannot be recouped is referred to as which type of cost? A. Fixed. B. Forgotten. C. Variable. D. Opportunity E. Sunk