Question: A Cost/Schedule graph can be interpreted using ___________ for its vertical axis and _______ for its horizontal axis. Multiple Choice Earned Value; Schedule. Dates; Actual

A Cost/Schedule graph can be interpreted using ___________ for its vertical axis and _______ for its horizontal axis. Multiple Choice Earned Value; Schedule. Dates; Actual Cost. Baseline; Deadline. Dollar Amounts; Time. None of these alternatives is correct