Question: a. Create a Network Planning from the below activities b. Calculate EET (earliest event time) c. Calculate LET (Latest event time) c. Define Critical Path

a. Create a Network Planning from the below

a. Create a Network Planning from the below activities b. Calculate EET (earliest event time) c. Calculate LET (Latest event time) c. Define Critical Path After C DE F No. Activity Code Duration Before 1 9 2 B 8 3 C 6 4 D 10 B 5 E 7 B 6 F 9 CD 7 G 5 E 8 H 11 F,G F G vou H | | | I H