Question: A critical activity occurs after every phase in DMAIC (Define, Measure, Analyze, Improve, and Control). This activity is designed, among other things, to review the
A critical activity occurs after every phase in DMAIC (Define, Measure, Analyze, Improve, and Control). This activity is designed, among other things, to review the teams progress and obtain a go or no-go decision on the project. Which of the following best describes this activity?
Plan-Do-Check-Act (or PDCA)
Tollgate review
Project charter review
Hypothesis testing