Question: A critical path for CPM with one time estimate is a sequence of activities between two events a collection of activities and events with a
A critical path for CPM with one time estimate is
| a sequence of activities between two events | ||
| a collection of activities and events with a definable beginning and end | ||
| A sequence of activities that form a continuous path between the start of a project and its completion where each of these activities has no slack | ||
| The sequence of activities that form a non-continuous path between the start of a project and its completion where some of these activities have no slack |