Question: A critical path for CPM with one time estimate is a sequence of activities between two events a collection of activities and events with a

A critical path for CPM with one time estimate is

a sequence of activities between two events

a collection of activities and events with a definable beginning and end

A sequence of activities that form a continuous path between the start of a project and its completion where each of these activities has no slack

The sequence of activities that form a non-continuous path between the start of a project and its completion where some of these activities have no slack