Question: A customer indicates that they would like to add a functionality to a product in development. Although this request is made during the execution stage
A customer indicates that they would like to add a functionality to a product in development. Although this request is made during the execution stage of the project, the project manager determines that the cost for the addition would be small. The additional functionality, if successful, would increase the opportunity for profit. What should the project manager do next?
Question options:
Move forward, using the projects management reserve to add the requested functionality
Submit a change request and then evaluate the impact to the project.
Identify and alreadydeveloped feature that could be combined with the new functionality, and use the combination to meet the customer's request.
Acknowledge that the functionality would offer a great opportunity, but determine that the proposed addition is out of scope.
Add it to the product backlog for future refinement.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock