A decision is being made to select the best contractor (out of the three contenders) based on three criteria: experience, tender price and technique. Using the AHP technique, a diagram has been produced as below.
Assuming "Tender Price" is the only criterion used, which is the best contractor?
Contractor A
Contractor B
Contractor C
Cannot be determined